Timescales may change as the project progresses but the programme currently is as follows:

Milestone Timescales
Public consultation (3 stages) Summer 2014 until summer 2015
Planning application submitted Spring 2015
Planning decision by Lambeth Council’s planning committee October 2015
Construction starts on Phase 1A (Town Hall, the Press building and Town Hall Parade) Spring 2016
Construction starts on Phase 1B (Hambrook House and Ivor House) Feb 2017
Works complete on the Town Hall and re-opened to the public Jan 2018
Works complete on the rest of Phase 1A (the Press building and Town Hall Parade) Feb 2018
Works complete on Phase 1B (Hambrook House and Ivor House) Targeting late 2018
Construction starts on Phase 2 (Olive Morris House) Late 2018
Works complete on Phase 2 (Olive Morris House) Late 2020